Setup ​

Location on ribbon: Tab DVD Cons → Group Schedule

Command ID: btnGanttSetupGroup

What it does ​

Opens the Gantt Setup tool window, which gathers three tabs: Work Calendar (working weekdays, public holidays), Gantt Settings (how the Gantt chart is drawn) and Show/Hide Columns on the schedule sheet.

Reach for it when the chart does not come out the way you want: wrong default scale, Sundays counted as working days, or too many columns cluttering the printout.

How to use ​

  1. Open a workbook that contains a schedule sheet.
  2. Go to the DVD Cons tab → Schedule group → click Setup.
  3. The DVD Add-in - Gantt Setup window opens straight on the Gantt Settings tab.
  4. Pick the tab you need:
    • Work Calendar — declare the working weekdays and the non-working days / holidays used when scheduling.
    • Gantt Settings — the Gantt drawing parameters, split into Display / Colors / Size & Font / Shapes / Advanced.
    • Show/Hide Columns — choose which columns show on the schedule sheet.
  5. Click Save on the tab you changed (Apply on the Show/Hide Columns tab), then click Gantt Chart so the chart picks up the new configuration.

Video tutorial ​

Narrated in Vietnamese, with Vietnamese subtitles. Cài đặt tiến độ, Mẫu, Ngôn ngữ tiêu đề · 6 min 52 s · 15 cases · Download the video · Practice workbook for the video

Commands in this video: Setup · Calendar Setup · Gantt Tpl · Header Language

Chapters (19)
  1. Giới thiệu
  2. Mở lệnh
  3. 1 · Đổi tiêu đề Anh → Việt
  4. 2 · Bảng lẫn hai thứ tiếng
  5. 3 · Bảng không phải tiến độ
  6. 4 · Cửa sổ Cài đặt – ba thẻ
  7. 5 · Hiển thị, màu, thang
  8. 6 · Đường găng
  9. 7 · Từ khoá tài nguyên
  10. 8 · Tuần làm việc 5 ngày
  11. 9 · Ngày lễ, ngày nghỉ riêng
  12. 10 · Lưu theo sổ hay theo máy
  13. 11 · Ẩn/Hiện cột
  14. 12 · Sắp xếp cột, Ctrl+Z
  15. 13 · Mẫu tiến độ → sổ mới
  16. 14 · Không tìm thấy mẫu
  17. 15 · Sheet đang khoá
  18. Mẹo
  19. Kết thúc

Illustrated walkthrough ​

Step 1. On the ribbon, open the DVD Cons tab → Schedule group → click Setup.

DVD Cons ▸ Schedule ▸ Setup

Step 2. The DVD Add-in - Gantt Setup window opens straight on the Gantt Settings tab (between the Work Calendar and Show/Hide Columns tabs). It is split into Display / Colors / Size & Font / Shapes / Advanced — e.g. tick Draw Today line (current date) (1) and click Save (2).

Step 2

Step 3. Work Calendar tab: click Mon → Sat (VN site — 6 days) (1), pick the year and click Apply VN holidays (2) — the table is filled with the 11 statutory holidays of 2026 (New Year, five days of Tết, Hùng Kings, 30/4, 1/5, 1–2/9); add your own dates with + Add. Click Save (3). This calendar drives every scheduling command, including Auto Calc and Constraints.

Step 3

Step 4. Show/Hide Columns tab: tick or untick the columns to show on the schedule sheet (hiding never deletes data). Re-ordering uses Excel's Cut–Insert and therefore the clipboard — if the clipboard holds something the add-in asks first, and the Confirm data change box offers to back up the sheet.

Step 5. The existing chart does not pick up the new settings by itself: run Gantt Chart again (or turn on Auto Draw and edit a cell) to apply them.

Example ​

Your site works Saturdays, rests on Sundays and observes the Vietnamese public holidays (Tết, 30 April, 1 May, 2 September). The default schedule counts Sundays as working days, so every finish date comes out earlier than reality.

Click Setup → open Work Calendar → remove Sunday from the working days and add the year's holidays. Save, go back and click Gantt Chart — every long activity's finish date stretches out to the true number of working days.

Notes ​

  • Show/Hide columns tab — changing the column order uses Excel's Cut–Insert (the only way every formula keeps pointing at the right column), so it goes through the clipboard: if the clipboard holds something you copied, the add-in asks first (that content will be lost) — paste it, then reorder. Merely showing/hiding columns never touches the clipboard.
  • Draw baseline bars (thin, grey) under the current bars (Gantt settings tab, time-aids group): dates come from the sheet's current baseline (Baseline), matched by Activity ID. Off by default.
  • The working calendar affects every scheduling command, including Auto Calc and Constraints — recalculate the sheet after changing it.
  • Changing settings does not repaint an existing chart on its own; click Gantt Chart (or turn on Auto Draw and edit a cell) to see the effect.
  • If the window cannot open, the add-in shows an error dialog with the exact message — usually because no workbook is open or the Excel session is busy.
  • Hiding a column only changes what is displayed; the data in that column is untouched.
  • Gantt Chart — apply the settings you just changed to the chart.
  • Auto Calc — uses the very working calendar defined here.
  • Header Language — switch column headers between Vietnamese and English after choosing which are visible.
  • Gantt Tpl — a ready-made template if you would rather start from the standard layout.