EVM Report
Location on ribbon: Tab DVD Cons → Group Schedule → Menu Reports & Snapshot
Command ID: btnEvmReport
PRO feature
This command is part of the PRO plan. STANDARD accounts activated before 01/07/2026 keep access until their licence expires; other Standard accounts get an upgrade prompt when they click it.
What it does
Runs an Earned Value Management analysis from three things already on the schedule sheet: each activity's budget (BAC), actual cost (AC) and percent complete. It writes a new sheet with the standard PMI metric table plus a three-line S-curve chart (PV / EV / AC). Use it when you have to answer the owner's classic questions: are we behind or ahead, are we over or under budget, and what will this package finally cost.
How to use
- Open a schedule sheet that has the BAC column (column N in the 20-column template). If it is missing, run Upgrade Sheet in the Setup group first.
- Fill in actual cost (AC) and bring percent complete up to your data date.
- Go to Tab DVD Cons → group Schedule → menu Reports & Snapshot → click EVM Report.
- The command runs immediately — no dialog. A new report sheet is created and activated.
- Read the metric table: BAC, PV, EV, AC, SV, CV, SPI, CPI, EAC, ETC, VAC. SPI/CPI cells are colour-coded green when ≥ 1, yellow between 0.9 and 1, red below 0.9.
- Scroll down for the weekly cumulative table and the S-curve chart: PV as a blue dashed line, EV in green, AC in red.
Example
Superstructure package on an apartment project, total BAC 12.5 bn VND, data date end of June:
| Metric | Value | Meaning |
|---|---|---|
| BAC | 12.50 bn | Total package budget |
| PV | 7.20 bn | Planned value at the data date |
| EV | 6.48 bn | Value actually earned |
| AC | 7.10 bn | Money actually spent |
| SPI | 0.90 | Yellow cell — roughly 10% behind |
| CPI | 0.91 | Red cell — running over budget |
| EAC | 13.73 bn | Forecast cost at completion |
The S-curve shows EV separating from PV in week 9 — exactly when rebar deliveries slipped, which is enough evidence for the delay notification letter.
Notes
- The BAC column is mandatory; without it the command cannot compute and reports an error.
- If AC is left empty, CPI, CV and EAC are meaningless — only the schedule side (SPI/SV) can be trusted.
- EV is derived from percent complete, so update status before running to keep the report tied to your data date.
- Each run regenerates the report; Ctrl+Z will not undo the created sheet and chart.
- The S-curve is a native Excel chart — you can restyle it, retitle it or paste it into Word/PowerPoint.
Related
- Variance Dashboard — folds EVM and schedule variance into one management page.
- Cash-flow — spreads the same BAC over time for disbursement planning.
- Update Status — refresh percent complete before EV is calculated.
- Snapshot — store this week's SPI/CPI so trends can be tracked later.